OLMO782-WT808-001 is under construction

follow the build

Project Kick-off : 8th of March, 2021

Covid and its availibility and supply issues has disrupted many project plannings.
Ours as well.
Yet, the results are materialising to expectations.


Video per 16 June 2022

OLMO arrived at box builder

 

25 March 2021

This is where the panels will be made and box will be built.

 

The subframe phase 1

 

15 April 2021

we like a well equipped workshop. Our partner JDK has it all.

Floor

 

20 April 2021

Floor is build for sturdiness and stiffness - beams every 60cm

Floor and 2 walls put up

 

26 April 2021

Floor is laid and 2 walls are put up. First impression of size.

Box is up.

 

3 may 2021

rear garage, bulkheads and sides are up

Box goes on the Arocs

 

20 may 2021

box closed up. And on the Arocs

Ramp goes on the Arocs

 

4th of June 2021

and the loading ramp goes on - 1500kg capacity

 

Systems are moving ahead

 

4th of August 2021

After careful planning, the Victron Electrical Main Board is being assembled.

 

Interior feel defined

 

1st September 2021

Fabrics have been chosen

 

Interior progressing

 

4 november 2021

interior really showing its volumes and general feel

 
 

Water systems almost done

 

4 januari 2022

Everything its own place. Every circuit its own tap. 40L boiler tightly done

 

Windows are in

 

11 januari 2022

Windows fitted. Looking good!

 

At the paint shop

 

11 Februari 2022

Paint scheme and chassis storage being done

 
 
 
 

Victron wall done

 

19 April 2022

Victron wall in its place and done!

001 is alive!

 

11th May 2022

All is connected!

 

final touches

 

1 June 2022

coming together as envisioned!

Storage

 

6 June 2022

Clean and efficient. Organised and uncluttered storage. No filter Systems, no electrical equipment. Loads of storage

Box done!

 

20 June 2022

box is closed . all hatches in and done!